The TCC Seton Lake project is currently in the finishing stages.  The exterior paint is being touched up, the site sidewalks are in progress and the irrigation system is being installed in preparation for the landscaping.  The canopies are in progress and the glass storefronts are finishing up as well.  The building shell is on track to finish ahead of schedule at the end of October.  The office design is in the final stages and we anticipate being released for interior construction very soon.